Progress Report

COMPLETED

  • Repointing of external walls. The Conservation Officer has requested a darker, more neutral shade. The Conservation Officer will be present to approve the technique for stone cleaning of the north facade. This will take place on Tuesday 1st June 2010.
  • Lining has been applied to the auditorium upper wall instead of patch repairs to the lath and plaster. This will achieve a better finish
  • Pipework has been relocated in the auditorium within the skirting boards.

DUE FOR COMPLETION:

  • A more detailed colour scheme is to be approved by the board of Biggar Theatre Workshop.
  • The roof is to be made watertight to prevent water ingress. It is suggested that the lead be replaced by alwitra which has a 30 year guarantee. It is much easier to fit, being lighter in weight than lead and will be much easier to patch in future years if required.
  • Quotes from Sound and Lighting companies are due in.
  • A quote for re-instating the rose window with standard glass has been requested. In the meantime, this window has been plastered to the detail shape of the window.

OTHER ISSUES:

  • The architect has confirmed the additional costs of numbering the auditorium seats, and adding emergency lighting to the raked seating steps
  • A sub-group has been set up to progress heritage related items to meet the Heritage Lottery Fund application.
  • Discussions are underway in order to protect the building from damage from the annual Hogmanay Bonfire.
  • Some funding for Phase 2 has been secured. Other funding possibilities are Wind Farm funding (applications being accepted in October 2010) and Big Lottery Fund - Growing Community Assets Programme (launching in June 2010)